Project Timeline
July 1, 1999-June
30, 2000
- Define
project feasibility, scope, and requirements
- Determine
background data availability
- Installation:
select study sites, locate transects, and determine sampling protocol
- Data
collection:
Begin
temperature, hydraulic, and preliminary water quality data collection
- Analysis:
aerial photos, historic flows, topographic maps, habitat types and categories,
reach selection, biological species availability and location, existing
habitat suitability curves, and community information
July 1, 2000-June 30, 2001
- Data
collection:
continue hydraulic and temperature data collection, and begin habitat
data collection
- Analysis:
determine target species and fish sampling protocol, begin calibration
of hydraulic model
- Community
involvement:
begin discussions with water users on type of model output and use
July 1, 2001-June
30, 2002
- Data
Collection:
continue hydraulic, habitat, and temperature data collection
- Analysis:
continue calibration of hydraulic model; begin
development of suitability curves,
habitat modeling, and transferability
testing of habitat suitability curves
- Community
involvement:
continue discussions with stakeholders on type of model output and use
July 1, 2002-June
30, 2003
- Data
Collection:
Complete data collection
- Analysis:
complete calibration of hydraulic and habitat models, conduct time
series analysis of hydrologic and habitat data
- Community
involvement:
finalize discussions with stakeholders on type of model output and use
- June
2003:
Complete analysis of output and final report
|